Satellite Tracking Project

Satellite Tracking Project (LEO)

What we are deploying:

12 Oct 2018 – Last friday we were able to arrange some time with Derek to pull the cables the last ten feet. Yay! The issue was the size of the conduit. It carried three bundles of fiber up to the roof but they were in those stiff plastic protective tubing. In the picture, you can see two of the three with the third hiding behind them. Side note, Metricom with their Ricochet modems were one of the first companies to offer cellular data services at the start of the internet boom. If you are ever on the roof of Cory Hall, the conduit that runs along the perimeter were used for their antennas.

As you can see there was no space to pull additional cables through it. Derek allowed us to decommission a set so we could pull the cables through. Derek is a bit shy.

The original run just punched a hole through the wall … violating a few rules and irking a few of us regarding proper strain relief on cables.

Now, there is a proper fire stop and a waterfall for the cables on both sides of the wall.

So we’re getting a little closer. Kevin and Hall have been cleaning up the shack and testing various components before the actual deployment.

/update
I met with Hall Celine, Kevin, and Travis to go over the logistics of the installation.

20 Aug 2018 – We pulled the cables through the main part of the run today. Since this is the first week of classes, it may be a few days before we have a chance to finish pulling the last part of the run into the shack.

16 Aug 2018 – Everything has arrived and we have tested the rotator and controller. We have made arrangements with Derek to pull cables this week *fingers crossed* and final assembly might be as soon as next week.

A little premature, but I’d like to thank all of the students, especially Kevin, who started this process, and Hall who helped get it over the finish line. I’d also like to thank KG6NUB again for his patience as we slowly made our way to this point and for all of his invaluable guidance and wisdom. I’d also like to thank the people at M2 for their advice, Professor Prabal Dutta who has kindly arranged for cable management to be installed on the penthouse, Scott McNally, Logan Baldini, and Derek Calderon for their advice, guidance, and elbow grease to get this antenna up and running. Finally, a special thanks to Professor Miki Lustig for his guidance and making all of this possible.

6 Aug 2018 – All of the remaining cables and supplies have been ordered by Hall which have started to arrive. We are hoping to receive everything in the next week or two and can hopefully have the antenna up and running right as the semester starts.

2 Jul 2018 – Although we haven’t updated this page recently, we have been working continuously towards installing the hardware.

Location – We have met with and made arrangements with the building and facilities managers to proceed. Besides installing the antenna, Professor Dutta has graciously agreed to fund the installation of cable management trays/runways on the penthouse (Thank you, Prabal!). We have also met with the department network engineer to clean up the existing cabling.

Components – KG6NUB has provided us with many recommendations regarding hardware and cabling. We went with his recommendation and picked up an ICOM IC 910H, KP-2/2M and KP-2/440 Preamps, and an M2 LEO-pack.

Cabling – Besides KG6NUB’s recommendation, we contacted M2, the antenna manufacturer, asking their recommendations about cabling. This is a concern because the run is so long, 130′ from shack to the top of the mast, and we wanted to make sure we crossed our t’s and dotted our i’s before purchasing cabling. Another important concern that KG6NUB brought up and KK6MRI reminded us is the flexibility of the cable. When you are tracking satellites, cables need to be able to endure repeated flexing but the jacket on flexible cables are not as rugged as their non-flexible siblings. Once we finalize the cabling selection, I will update this page.

31 May 2018 – We are still in the process of installing the hardware. Kevin has already sourced all the hardware and we are currently planning the installation. We are hoping to have everything installed before the end of summer *fingers-crossed*

You can always join the Slack Channel!